Phase entity duration should affect 'End Date'

When planning inside of the ‘Phases’ page in a project, the ‘End Date’ field shouldn’t be mandatory.

It should be possible to create a Phase entity with a ‘Start Date’ and a ‘Duration’, and the ‘End Date’ would be adjusted according to this duration.

It would also be nice for those phases durations to consider weekends, and ignore them inside of the ‘Project Timeline’ page.
A 80h phase would be split in two weeks, from monday to friday, for example.

1 Like

ST Discussion: marinating post that could use some input :woman_cook:

Hi @cblanchette!

I can definitely see how those would be useful enhancements to Phases in the Project Timeline app. I’d recommend submitting them as ideas via our roadmap site. More details on that are here:

1 Like

Alright, I submitted the request to the public roadmap.

Thanks!